Assessment Activities
Property Name | EPA Funding | Completion Date | Activity | Leveraged Funding |
222 East Irving Blvd | $40,933.00 | 06/19/2014 | Phase II Environmental Assessment | $31,880.00 |
Former Central Freight Facility | $51,855.00 | 06/27/2014 | Phase II Environmental Assessment | $0.00 |
Heritage Crossing - Nine Residential Properties | $24,553.00 | 01/06/2014 | Phase II Environmental Assessment | $0.00 |
Heritage Park Area | $6,380.00 | 05/19/2014 | Phase II Environmental Assessment | $0.00 |
Tract 9 | $23,700.00 | | Cleanup Planning | $406.00 |
Tract 9 | $25,180.00 | 12/08/2014 | Phase II Environmental Assessment | $0.00 |
Tract 9 | $9,494.00 | 06/09/2015 | Supplemental Assessment | $0.00 |
EPA Assessment Funding: $182,095.00
Leveraged Funding: $32,286.00
Total Funding: $214,381.00
NOTE: Funding marked for deletion not included in totals
Top of Page