1002 S. Whitney Way | $4,017.00 | 06/04/2015 | Phase I Environmental Assessment | $0.00 |
1102 N Sherman Ave | $4,517.00 | 09/30/2015 | Phase I Environmental Assessment | $0.00 |
1102 N Sherman Ave | $28,154.00 | 11/06/2015 | Phase II Environmental Assessment | $0.00 |
1102 N Sherman Ave | $12,826.00 | 02/05/2016 | Supplemental Assessment | $0.00 |
2340 Winnebago | $4,621.00 | 09/01/2016 | Phase I Environmental Assessment | $0.00 |
2340 Winnebago | $7,400.00 | 09/23/2016 | Phase II Environmental Assessment | $0.00 |
56 Corry St. | $4,897.00 | 09/06/2016 | Phase I Environmental Assessment | $0.00 |
709 Rethke Ave. | $2,000.00 | 04/01/2015 | Cleanup Planning | $0.00 |
709 Rethke Ave. | $5,000.00 | 07/01/2014 | Phase I Environmental Assessment | $0.00 |
709 Rethke Ave. | $12,049.00 | 10/01/2014 | Phase II Environmental Assessment | $0.00 |
722 Williamson | $5,000.00 | 11/19/2013 | Phase I Environmental Assessment | $0.00 |
722 Williamson | $16,557.00 | 04/01/2014 | Phase II Environmental Assessment | $0.00 |
722 Williamson | $0.00 | 07/27/2016 | Supplemental Assessment | $7,616.00 |
Don Miller South | $8,884.00 | 09/30/2016 | Cleanup Planning | $0.00 |
Don Miller South | $15,626.00 | 09/14/2015 | Phase II Environmental Assessment | $0.00 |
Don Miller South | $19,734.00 | 07/31/2016 | Supplemental Assessment | $0.00 |
Former Savidusky Furriers and Cleaners | $4,000.00 | 05/02/2014 | Phase I Environmental Assessment | $0.00 |
Former Savidusky Furriers and Cleaners | $7,214.00 | 10/14/2014 | Phase II Environmental Assessment | $0.00 |
Garver Feed Mill | $17,491.00 | 09/16/2015 | Phase I Environmental Assessment | $0.00 |
Jacobson-Furey | $5,954.00 | 11/13/2014 | Phase I Environmental Assessment | $0.00 |
Jacobson-Furey | $0.00 | 12/01/2014 | Phase II Environmental Assessment | $5,000.00 |
Judge Doyle Square | $6,045.00 | 10/06/2015 | Phase I Environmental Assessment | $0.00 |
Land O'Lakes Madison Dairy | $3,000.00 | 03/07/2016 | Cleanup Planning | $0.00 |
Land O'Lakes Madison Dairy | $44,528.00 | 02/23/2016 | Phase II Environmental Assessment | $0.00 |
Madison Brassworks | $5,000.00 | 11/14/2014 | Phase I Environmental Assessment | $0.00 |
Madison Brassworks | $13,430.00 | 01/11/2015 | Phase II Environmental Assessment | $0.00 |
Reynolds Crane Lot | $6,000.00 | 06/01/2015 | Cleanup Planning | $0.00 |
Reynolds Crane Lot | $19,798.00 | 04/01/2014 | Phase II Environmental Assessment | $0.00 |
Reynolds Crane Lot | $52,959.00 | 01/07/2015 | Supplemental Assessment | $0.00 |