29th & Douglas Shoppes | $8,072.50 | 02/07/2024 | Phase I Environmental Assessment | $0.00 |
29th & Douglas Shoppes | $89,832.59 | 06/13/2024 | Phase II Environmental Assessment | $0.00 |
Ames Texaco | $5,000.00 | 03/01/2024 | Phase I Environmental Assessment | $0.00 |
Ames Texaco | $69,008.50 | 08/19/2024 | Phase II Environmental Assessment | $0.00 |
Birdsell Tire Shop | $7,000.00 | 08/03/2023 | Phase I Environmental Assessment | $0.00 |
Birdsell Tire Shop | $306,029.36 | 06/14/2024 | Phase II Environmental Assessment | $0.00 |
Campus Corner Site | $10,262.50 | 05/04/2023 | Phase I Environmental Assessment | $0.00 |
Campus Corner Site | $56,297.86 | 10/30/2023 | Phase II Environmental Assessment | $0.00 |
Deep Rock Project | $7,000.00 | 05/08/2024 | Phase I Environmental Assessment | $0.00 |
Deep Rock Project | $50,707.04 | 11/26/2024 | Phase II Environmental Assessment | $0.00 |
Elk City - Elk Elevator | $5,000.00 | 06/06/2024 | Phase I Environmental Assessment | $0.00 |
Elk City - Elk Elevator | $85,946.54 | 07/11/2024 | Phase II Environmental Assessment | $0.00 |
June's Restaurant | $55,495.61 | 08/21/2023 | Phase II Environmental Assessment | $0.00 |
Midwest City Auto | $5,187.50 | 01/22/2024 | Phase I Environmental Assessment | $0.00 |
Midwest City Auto | $60,541.41 | 07/11/2024 | Phase II Environmental Assessment | $0.00 |
Rock Island and Wade Project | $5,000.00 | 11/07/2023 | Phase I Environmental Assessment | $0.00 |
Rock Island and Wade Project | $97,960.94 | 10/16/2024 | Phase II Environmental Assessment | $0.00 |
Roy D. Feltman Cordell Total | $5,000.00 | 08/09/2023 | Phase I Environmental Assessment | $0.00 |
Roy D. Feltman Cordell Total | $52,682.04 | 04/07/2024 | Phase II Environmental Assessment | $0.00 |
Village Market | $7,000.00 | 08/16/2023 | Phase I Environmental Assessment | $0.00 |
Village Market | $80,681.70 | 04/29/2024 | Phase II Environmental Assessment | $0.00 |