137465
A E Backus Avenue / 101 Avenue C Fort Pierce, FL 34950
.69
2410-503-0012-010-9
27.451057 / -80.325008
21
Ward, Jon
jward@city-ftpierce.com
772-460-2200


Top of Page


Property Location



Top of Page


Property Progress


Top of Page


CAs Associated with this Property

CA NameCA #StateTypeAnnouncement Year
Fort Pierce Redevelopment AgencyBF95460810FLCleanup2010


Top of Page


Assessment Activities at this Property

There are no current assessment activities.


Is Cleanup Necessary?
EPA Assessment Funding:
Leveraged Funding:
Total Funding:


Top of Page


Climate Adaption and Mitigation - Planning or Assessment

There is no data for Climate Adaption and Mitigation - Planning or Assessment.


Top of Page


Contaminants and Media


PCBS
Petroleum Products
Cleaned Up
Cleaned Up
Soil
Cleaned Up

Cleanup Activities

Start DateEPA FundingCompletion DateCAAccomplishment Counted?Cleanup Documentation
01/01/2011$200,000.0006/14/2013Fort Pierce Redevelopment AgencyYes


Cleanup/Treatment Implemented:
Cleanup/Treatement Categories:
Addl Cleanup/Treatment info:
Address of Data Source:
Total ACRES Cleaned Up: .69
Number of Cleanup Jobs Leveraged: 50
EPA Cleanup Funding: $200,000.00
Leveraged Funding:
Cost Share Funding:
Total Funding: $200,000.00


Top of Page


Climate Adaption and Mitigation - Demolition or Cleanup

There is no data for Climate Adaption and Mitigation - Demolition or Cleanup.


Top of Page


Institutional and Engineering Controls

No
No
No
No


Top of Page


Redevelopment and Other Leveraged Accomplishments

There are no current redevelopment activities.


Number of Redevelopment Jobs Leveraged:
Actual Acreage of Greenspace Created:
Leveraged Funding:


Top of Page


Climate Adaption and Mitigation - Redevelopment

There is no data for Climate Adaption and Mitigation – Redevelopment


Top of Page


Additional Property Attributes

Cleanup activities at this site included source removal of co-mingled petroleum and PCB-impacted soils. Based on the Combined Document Site Assessment and Interim Source Removal Report dated 06/14/2013; the site met the conditions for a non-conditional Site Rehabilitation Compleion Order. The SRCO was issued by the FDEP on 07/16/2013.

Former Use: Part of former HD King Power Plant
Industry (.69)
Hazardous