Cleanup/Treatment Implemented:
Y
Cleanup/Treatement Categories:
Addl Cleanup/Treatment info:
The remedial approach will focus on the treatment of groundwater impacted with CVOCs on the Site. ISCO methods for the treatment of impacted groundwater entail injection of a strong oxidant into the groundwater to chemically remediate CVOCs. A small scale SVE pilot test was was implemented 4/4/2022. The SVE system was expanded in October 2022. Bi-annual ISCO injections and groundwater monitoring have been conducted since that time. Additional remedial options are being considered.
Address of Data Source:
Total ACRES Cleaned Up: 3.7
Number of Cleanup Jobs Leveraged:
EPA Cleanup Funding:
Leveraged Funding:
Cost Share Funding:
Total Funding: