Cleanup Activities
Start Date | EPA Funding | Completion Date | CA | Accomplishment Counted? | Cleanup Documentation |
10/11/2022 | | 04/10/2023 | City of Toledo | No | |
10/11/2022 | | 04/10/2023 | City of Toledo | No | |
Cleanup/Treatment Implemented:
Y
Cleanup/Treatement Categories:
Addl Cleanup/Treatment info:
Removal and disposal of all asbestos containing materials, removal and disposal of approximately 190 mercury light tubes and PCB ballasts, and 4 mercury thermostats. In May 2023 additional ACM material was removed and disposed of due to structure fire.
Address of Data Source:
Total ACRES Cleaned Up: .85
Number of Cleanup Jobs Leveraged: 6
EPA Cleanup Funding:
Leveraged Funding: $164,772.00
Cost Share Funding:
Total Funding: $164,772.00