Cleanup Activities
Start Date | EPA Funding | Completion Date | CA | Accomplishment Counted? | Cleanup Documentation |
09/03/2021 | | | Green Bay Redevelopment Authority | No | |
09/03/2021 | $391.50 | | Green Bay Redevelopment Authority | No | |
Cleanup/Treatment Implemented:
Cleanup/Treatement Categories:
Addl Cleanup/Treatment info:
Buildings were demolished in September 2021. Contaminated soils remain capped with existing concrete/asphalt and compacted gravel. Full cleanup will be planned with future redevelopment. The City partnered with EPA on a reuse plan in 2020 for the South Broadway corridor, including this site. The reuse plan will guide future RFPs for redevelopment.
Address of Data Source:
Total ACRES Cleaned Up: .37
Number of Cleanup Jobs Leveraged: 0
EPA Cleanup Funding: $391.50
Leveraged Funding: $35,130.00
Cost Share Funding:
Total Funding: $35,521.50