235742
Shinn Boulevard LAKE ALFRED, FL 33850
.28
26-27-32-502000-000081
28.0876830 / -81.7304290
18
Jennings, Wanda
Jennings.Wanda@epa.gov
404-562-8682


Top of Page


Property Location



Top of Page


Property Progress


Top of Page


CAs Associated with this Property

CA NameCA #StateTypeAnnouncement Year
Central Florida Regional Planning CouncilBF95481311FLBCRLF2011
Central Florida Regional Planning CouncilBF00D25714FLAssessment2014


Top of Page


Assessment Activities at this Property

ActivityEPA FundingStart DateCompletion DateCAAccomplishment Counted?Counted When?
Phase I Environmental Assessment$3,200.0009/01/201609/29/2016Central Florida Regional Planning CouncilYFY18
Phase II Environmental Assessment$26,860.0002/01/201703/31/2017Central Florida Regional Planning CouncilN
Supplemental Assessment$33,850.0008/01/201708/25/2017Central Florida Regional Planning CouncilN


Is Cleanup Necessary? Yes
EPA Assessment Funding: $63,910.00
Leveraged Funding:
Total Funding: $63,910.00


Top of Page


Climate Adaption and Mitigation - Planning or Assessment

There is no data for Climate Adaption and Mitigation - Planning or Assessment.


Top of Page


Contaminants and Media


SVOCs
VOCs
Cleaned Up
Cleaned Up
Ground Water
Soil
Cleaned Up
Cleaned Up

Cleanup Activities

Start DateEPA FundingCompletion DateCAAccomplishment Counted?Cleanup Documentation
08/09/2019$79,800.0009/30/2020Central Florida Regional Planning CouncilNo


Cleanup/Treatment Implemented: Y
Cleanup/Treatement Categories:
Addl Cleanup/Treatment info:
Address of Data Source:
Total ACRES Cleaned Up: .28
Number of Cleanup Jobs Leveraged: 2
EPA Cleanup Funding: $79,800.00
Leveraged Funding:
Cost Share Funding:
Total Funding: $79,800.00


Top of Page


Climate Adaption and Mitigation - Demolition or Cleanup

Selected Strategy(ies)Explanatory Text
N/AThis property does not incorporate demolition or cleanup activities to address impacts from extreme weather events and natural disasters. If no activities were incorporated, select this option.


Top of Page


Institutional and Engineering Controls

No
End use not yet determined
No
No
No


Top of Page


Redevelopment and Other Leveraged Accomplishments

There are no current redevelopment activities.


Number of Redevelopment Jobs Leveraged:
Actual Acreage of Greenspace Created:
Leveraged Funding:


Top of Page


Climate Adaption and Mitigation - Redevelopment

There is no data for Climate Adaption and Mitigation – Redevelopment


Top of Page


Additional Property Attributes

A Phase I ESA completed in 2016 revealed RECs associated with the subject site based on historical land use (fruit packing warehouse with documented petroleum storage - likely for heat); as well as off-site land uses with the potential to impact the subject site (adjacent auto repair facilities and adjacent former railroad). Phase II and Supplemental Phase II ESAs conducted in 2017 revealed limited impacts to soil and groundwater near the site's SE corner. The source of these impacts could not be identified. Former Use: Historical use included a fruit packing warehouse Cleanup activity funded by CFRPC (via subgrant and loan) resulted in a Site Rehabilitation Completion Order without conditions in December 2020.
Industry (.28)
Hazardous & Petroleum
12/18/2020