250480
304 Vinnedge Avenue BLACKWELL, OK 74631
4.75
36.78675498663762 / -97.28764098011312
3
Reyes, Elizabeth
Reyes.Elizabeth@epa.gov
214-665-3163


Top of Page


Property Location



Top of Page


Property Progress


Top of Page


CAs Associated with this Property

CA NameCA #StateTypeAnnouncement Year
Oklahoma Department of Environmental QualityRP01F52801OKSection 128(a) State/Tribal2018


Top of Page


Assessment Activities at this Property

ActivityEPA FundingStart DateCompletion DateCAAccomplishment Counted?Counted When?
Cleanup Planning$19,222.1801/21/202109/27/2021Oklahoma Department of Environmental Quality
Phase II Environmental Assessment$13,007.4801/02/202109/27/2021Oklahoma Department of Environmental QualityYFY22


Is Cleanup Necessary? Yes
EPA Assessment Funding: $32,229.66
Leveraged Funding:
Total Funding: $32,229.66


Top of Page


Climate Adaption and Mitigation - Planning or Assessment

There is no data for Climate Adaption and Mitigation - Planning or Assessment.


Top of Page


Contaminants and Media


Asbestos
Lead
Cleaned Up
NOT Cleaned up
Building Materials
Cleaned Up

Cleanup Activities

Start DateEPA FundingCompletion DateCAAccomplishment Counted?Cleanup Documentation
07/13/202209/19/2022Oklahoma Department of Environmental QualityNo


Cleanup/Treatment Implemented: Y
Cleanup/Treatement Categories:
Addl Cleanup/Treatment info: Asbestos abatement to remove friable asbestos. Non-friable asbestos and lead-based paint were left in place, because the building will be demolished in the future.
Address of Data Source:
Total ACRES Cleaned Up: 4.75
Number of Cleanup Jobs Leveraged: 10
EPA Cleanup Funding:
Leveraged Funding: $135,360.67
Cost Share Funding:
Total Funding: $135,360.67


Top of Page


Climate Adaption and Mitigation - Demolition or Cleanup

There is no data for Climate Adaption and Mitigation - Demolition or Cleanup.


Top of Page


Institutional and Engineering Controls

No
No


Top of Page


Redevelopment and Other Leveraged Accomplishments

There are no current redevelopment activities.


Number of Redevelopment Jobs Leveraged:
Actual Acreage of Greenspace Created:
Leveraged Funding:


Top of Page


Climate Adaption and Mitigation - Redevelopment

There is no data for Climate Adaption and Mitigation – Redevelopment


Top of Page


Additional Property Attributes

Former used as an elementary school. Lead-based paint and asbestos were found in the school. DEQ's state funded cleanup program only abated friable asbestos. Non-friable asbestos and lead-based paint were left in place, because the school will be demolished in the future.
Commercial (4.75)
Enrolled: 09/15/2021
Notification from DEQ SCAP program that cleanup was completed


Top of Page