Profile Information

Vaungarde Plant #1
Government
255863
1000 Bradley Street OWOSSO, MI 48867
3.12
050-660-008-001-00
42.99862950239026 / -84.1842052523701
7
Auker, Karla
auker.karla@epa.gov
440-250-1741


Top of Page


Property Location



Top of Page


Property Progress


Top of Page


CAs Associated with this Property

CA NameCA #StateTypeAnnouncement Year
Michigan Dept of Environment Great Lakes & Energy4B00E03214MIAssessment2022


Top of Page


Assessment Activities at this Property

ActivityEPA FundingStart DateCompletion DateCAAccomplishment Counted?Counted When?
Phase I Environmental Assessment$3,366.8903/01/202304/14/2023Michigan Dept of Environment Great Lakes & EnergyYFY24
Phase II Environmental Assessment$32,387.1005/25/202308/23/2023Michigan Dept of Environment Great Lakes & EnergyN


Is Cleanup Necessary? Unknown
EPA Assessment Funding: $35,753.99
Leveraged Funding:
Total Funding: $35,753.99


Top of Page


Climate Adaption and Mitigation - Planning or Assessment

Selected Strategy(ies)Explanatory Text
N/AThis property does not incorporate planning or assessment activities to address impacts from extreme weather events and natural disasters. If no activities were incorporated, select this option.


Top of Page


Contaminants and Media


Arsenic
Copper (Cu)
Lead
Mercury
Nickel (Ni)
Other Metals
PAHS
Petroleum Products
Selenium (Se)
VOCs
NOT Cleaned up
NOT Cleaned up
NOT Cleaned up
NOT Cleaned up
NOT Cleaned up
NOT Cleaned up
NOT Cleaned up
NOT Cleaned up
NOT Cleaned up
NOT Cleaned up
Ground Water
Soil
NOT Cleaned up
NOT Cleaned up

Cleanup Activities

There are no current cleanup activities.


Cleanup/Treatment Implemented:
Cleanup/Treatement Categories:
Addl Cleanup/Treatment info:
Address of Data Source:
Total ACRES Cleaned Up: 3.12
Number of Cleanup Jobs Leveraged:
EPA Cleanup Funding:
Leveraged Funding:
Cost Share Funding:
Total Funding:


Top of Page


Climate Adaption and Mitigation - Demolition or Cleanup

Selected Strategy(ies)Explanatory Text
N/AThis property does not incorporate demolition or cleanup activities to address impacts from extreme weather events and natural disasters. If no activities were incorporated, select this option.


Top of Page


Institutional and Engineering Controls



Top of Page


Redevelopment and Other Leveraged Accomplishments

There are no current redevelopment activities.


Number of Redevelopment Jobs Leveraged:
Actual Acreage of Greenspace Created:
Leveraged Funding:


Top of Page


Climate Adaption and Mitigation - Redevelopment

There is no data for Climate Adaption and Mitigation – Redevelopment


Top of Page


Additional Property Attributes

The Site was used as a lumberyard into the 1900's and was then utilized for manufacturing, painting, a foundry, production of hydraulic parts and equipment repair. A fire in 2004 destroyed both on site buildings.

The Phase I ESA identified the following recognized environmental conditions (RECs): 1) past industrial use, 2) semi-volatiles and metals identified during in shallow soil above cleanup criteria during 2006 subsurface investigation, 3) former fuel tank, 4) wastewater containing acetone, 5) former use of a solvent tank, 6) railroad spurs and associated concerns, 7) fire in 2004 that may have resulted in release of hazardous substances and/or petroleum products.

The Phase II ESA identified volatiles, semi-volatiles, and metals in soil and groundwater at concentrations exceeding both residential and non-residential cleanup criteria.
Industry (3.12)
ID Number (if Applicable): 78000141 Enrolled:


Top of Page