Profile Information

Paramount Theatre
Private
257029
422 N. Huron Street TOLEDO, OH 43604
2.11
15-00072
41.653847001332 / -83.535099981136
9
Stimple, Bradley
stimple.brad@epa.gov
440-250-1717


Top of Page


Property Location



Top of Page


Property Progress


Top of Page


CAs Associated with this Property

CA NameCA #StateTypeAnnouncement Year
City of Toledo4B00E03228OHAssessment2022


Top of Page


Assessment Activities at this Property

ActivityEPA FundingStart DateCompletion DateCAAccomplishment Counted?Counted When?
Phase II Environmental Assessment$13,250.0005/30/202308/14/2023City of ToledoYFY23


Is Cleanup Necessary? Yes
EPA Assessment Funding: $13,250.00
Leveraged Funding:
Total Funding: $13,250.00


Top of Page


Climate Adaption and Mitigation - Planning or Assessment

Selected Strategy(ies)Explanatory Text
N/AThis property does not incorporate planning or assessment activities to address impacts from extreme weather events and natural disasters. If no activities were incorporated, select this option.


Top of Page


Contaminants and Media


Arsenic
Cadmium (Cd)
Chromium (Cr)
Lead
Other Metals
NOT Cleaned up
NOT Cleaned up
NOT Cleaned up
NOT Cleaned up
NOT Cleaned up
Ground Water
Soil
NOT Cleaned up
NOT Cleaned up

Cleanup Activities

There are no current cleanup activities.


Cleanup/Treatment Implemented: N
Cleanup/Treatement Categories:
Addl Cleanup/Treatment info:
Address of Data Source:
Total ACRES Cleaned Up: 2.11
Number of Cleanup Jobs Leveraged:
EPA Cleanup Funding:
Leveraged Funding:
Cost Share Funding:
Total Funding:


Top of Page


Climate Adaption and Mitigation - Demolition or Cleanup

Selected Strategy(ies)Explanatory Text
N/AThis property does not incorporate demolition or cleanup activities to address impacts from extreme weather events and natural disasters. If no activities were incorporated, select this option.


Top of Page


Institutional and Engineering Controls

No
U
No


Top of Page


Redevelopment and Other Leveraged Accomplishments

There are no current redevelopment activities.


Number of Redevelopment Jobs Leveraged:
Actual Acreage of Greenspace Created:
Leveraged Funding:


Top of Page


Climate Adaption and Mitigation - Redevelopment

Selected Strategy(ies)Explanatory Text
N/AThis property does not incorporate redevelopment activities to address impacts from extreme weather events and natural disasters. If no activities were incorporated, select this option.


Top of Page


Additional Property Attributes

Consultant completed a Phase I ESA and a Phase II ESA for the site in 2016. The Phase I ESA for the parking lot portion of the site identified the use of the northerly adjoining property beyond Jackson Street (501-513 N. Superior Street) as a lead paint and varnish manufacturer from 1905 to the 1950s (Dolphin Lead Works) and the use of the westerly adjoining property beyond Huron Street (415 Huron Street) as a clothing cleaner from at least 1956 to 1975 as Recognized Environmental Conditions (RECs).

A prior Phase II IESA conducted in 2016 identified concentrations of lead in the northeastern/eastern corner of the parking lot portion of the site from eight to 12 feet bgs above the VAP Residential and Construction/Excavation GDCS. In addition, benzo(a)pyrene was also detected above the VAP Residential GDCS in this area. During this Phase II ESA, soil borings were located in the previously identified lead-impacted area to further evaluate the extent of the lead impacts. Lead was detected in two samples; one from four to six feet bgs and one from eight to ten feet bgs at concentrations above the VAP Residential and Construction/Excavation GDCS. The lead-impacted area appears to be a maximum of 50 feet long by 20 feet wide. The depth varies from a minimum of 6 feet to a maximum of 12 feet bgs. Any soils in this area disturbed during future renovation activities should be sampled prior to disposal. Construction/excavation workers conducting activities in this portion of the site should be notified of the lead-impacted soil and a health and safety plan should be prepared for worker protection.


Top of Page