853 & 1166 East Elmore Road WOLCOTT, VT 05680
334.4
44.530360980206 / -72.45844603165
1
McKeown, Amy
McKeown.AmyJean@epa.gov
617-918-1248


Top of Page


Property Location



Top of Page


Property Progress


Top of Page


CAs Associated with this Property

CA NameCA #StateTypeAnnouncement Year
Vermont Department of Environmental ConservationRP00A01255VTSection 128(a) State/Tribal2023


Top of Page


Assessment Activities at this Property

ActivityEPA FundingStart DateCompletion DateCAAccomplishment Counted?Counted When?
Supplemental Assessment$22,109.0004/16/202412/31/2024Vermont Department of Environmental ConservationYFY25


Is Cleanup Necessary? Yes
EPA Assessment Funding: $22,109.00
Leveraged Funding:
Total Funding: $22,109.00


Top of Page


Climate Adaption and Mitigation - Planning or Assessment

Selected Strategy(ies)Explanatory Text
Evaluate Reuse options that consider impacts from extreme weather events and natural disastersDiscussion of observed and forecasted natural hazard conditions and the associated site-specific risk are part of any reuse considerations. Both current and forecasted extreme weather events and natural disasters may impact the effectiveness of a remedial alternative.


Top of Page


Contaminants and Media


Other Contaminants
Cleaned Up

Cleanup Activities

Start DateEPA FundingCompletion DateCAAccomplishment Counted?Cleanup Documentation
09/01/2024$24,251.5010/31/2024Vermont Department of Environmental ConservationYes


Cleanup/Treatment Implemented: Y
Cleanup/Treatement Categories:
Addl Cleanup/Treatment info:
Address of Data Source:
Total ACRES Cleaned Up: 334.4
Number of Cleanup Jobs Leveraged: 0
EPA Cleanup Funding: $24,251.50
Leveraged Funding:
Cost Share Funding:
Total Funding: $24,251.50


Top of Page


Climate Adaption and Mitigation - Demolition or Cleanup

Selected Strategy(ies)Explanatory Text
Design of cleanup allowed for siting of weather-related and disaster-related resiliency measures in site reuseThe capacity of a system to maintain function in the face of stresses imposed by extreme weather events and natural disasters and to adapt the system to be better prepared for future related impacts.


Top of Page


Institutional and Engineering Controls

No
No


Top of Page


Redevelopment and Other Leveraged Accomplishments

There are no current redevelopment activities.


Number of Redevelopment Jobs Leveraged:
Actual Acreage of Greenspace Created:
Leveraged Funding:


Top of Page


Climate Adaption and Mitigation - Redevelopment

Selected Strategy(ies)Explanatory Text
N/AThis property does not incorporate redevelopment activities to address impacts from extreme weather events and natural disasters. If no activities were incorporated, select this option.


Top of Page


Additional Property Attributes

Future use as community forest, watershed protection area.
Greenspace (334)
ID Number (if Applicable): 20235368 Enrolled:
01/17/2025


Top of Page