Skip to Main Content
U.S. flag

An official website of the United States government


Profile Information

Stevensville Library
Government
265509
208 Main Street STEVENSVILLE, MT 59870
.2
13-1764-27-1-12-09-0000
46.510840457171 / -114.093007153875
999
Davis, Gregory
Davis.Gregory@epa.gov
303-312-6314


Top of Page


Property Location



Top of Page


Property Progress


Top of Page


CAs Associated with this Property

CA NameCA #StateTypeAnnouncement Year
MT Department of Environmental Quality4B95815270MTAssessment2022
Montana Department of Environmental Quality4W96873701MTSection 128(a) State/Tribal2022


Top of Page


Assessment Activities at this Property

ActivityEPA FundingStart DateCompletion DateCAAccomplishment Counted?Counted When?
Phase I Environmental Assessment$3,500.0001/24/202307/21/2023MT Department of Environmental QualityYFY25
Phase II Environmental Assessment$23,926.1001/24/202308/18/2023MT Department of Environmental QualityN


Is Cleanup Necessary? Yes
EPA Assessment Funding: $27,426.10
Leveraged Funding:
Total Funding: $27,426.10


Top of Page


Climate Adaption and Mitigation - Planning or Assessment

Selected Strategy(ies)Explanatory Text
N/AThis property does not incorporate planning or assessment activities to address impacts from extreme weather events and natural disasters. If no activities were incorporated, select this option.


Top of Page


Contaminants and Media


Asbestos
Lead
Cleaned Up
Cleaned Up
Building Materials
Cleaned Up

Cleanup Activities

Start DateEPA FundingCompletion DateCAAccomplishment Counted?Cleanup Documentation
07/29/2024$30,787.9610/25/2024Montana Department of Environmental QualityYes


Cleanup/Treatment Implemented: Y
Cleanup/Treatement Categories:
Addl Cleanup/Treatment info: Limited scope asbestos abatement and lead-based paint encapsulation to ensure safe daily operations of the library for staff and the public. A follow up inspection was conducted in February 2025 (report received on 3/13/2025) to verify protectiveness of abatement actions.
Address of Data Source:
Total ACRES Cleaned Up: .2
Number of Cleanup Jobs Leveraged: .02
EPA Cleanup Funding: $30,787.96
Leveraged Funding:
Cost Share Funding:
Total Funding: $30,787.96


Top of Page


Climate Adaption and Mitigation - Demolition or Cleanup

There is no data for Climate Adaption and Mitigation - Demolition or Cleanup.


Top of Page


Institutional and Engineering Controls

No
No


Top of Page


Redevelopment and Other Leveraged Accomplishments

There are no current redevelopment activities.


Number of Redevelopment Jobs Leveraged:
Actual Acreage of Greenspace Created:
Leveraged Funding:


Top of Page


Climate Adaption and Mitigation - Redevelopment

Selected Strategy(ies)Explanatory Text
N/AThis property does not incorporate redevelopment activities to address impacts from extreme weather events and natural disasters. If no activities were incorporated, select this option.


Top of Page


Additional Property Attributes

Redevelopment plans for the North Valley Public Library include either rebuilding at the current location or acquiring an alternate desirable location for building a new library for the Stevensville area. In either case, further cleanup of hazardous building materials at the current library will likely be necessary. Limited, small-scale abatement was conducted in 2024 to ensure safe ongoing operations at the current location for the time being.
Commercial (.2)
10/21/2024


Top of Page