184581
1102 South Washington Avenue Lansing, MI 48910
.36
33-01-01-21-178-040, 030, 021, 011
42.721625 / -84.552735
7
Didier, Matt
Didier.Matthew@epa.gov
312-353-2112


Top of Page


Property Location



Top of Page


Property Progress


Top of Page


CAs Associated with this Property

CA NameCA #StateTypeAnnouncement Year
City of LansingBF00E01076MIAssessment2012
City of Lansing BF00E02710MIAssessment2019


Top of Page


Assessment Activities at this Property

ActivityEPA FundingStart DateCompletion DateCAAccomplishment Counted?Counted When?
Cleanup Planning05/07/202106/21/2021City of Lansing N
Cleanup Planning$2,160.0011/20/202004/30/2021City of Lansing N
Cleanup Planning11/20/202004/30/2021City of Lansing N
Cleanup Planning$5,895.0005/07/202106/21/2021City of Lansing N
Phase I Environmental Assessment$2,500.0010/13/201410/24/2014City of LansingYFY16
Phase I Environmental Assessment$1,890.0003/27/202004/24/2020City of Lansing N
Phase I Environmental Assessment03/27/202004/24/2020City of Lansing N
Phase II Environmental Assessment$11,551.0011/14/201412/19/2014City of LansingN
Supplemental Assessment$3,600.0003/27/202004/29/2020City of Lansing N
Supplemental Assessment03/27/202004/29/2020City of Lansing N


Is Cleanup Necessary? No
EPA Assessment Funding: $27,596.00
Leveraged Funding: $1,505.00
Total Funding: $29,101.00


Top of Page


Climate Adaption and Mitigation - Planning or Assessment

There is no data for Climate Adaption and Mitigation - Planning or Assessment.


Top of Page


Contaminants and Media


Petroleum Products
VOCs
NOT Cleaned up
NOT Cleaned up
Ground Water
Air
Soil
NOT Cleaned up
NOT Cleaned up
NOT Cleaned up

Cleanup Activities

There are no current cleanup activities.


Cleanup/Treatment Implemented: N
Cleanup/Treatement Categories:
Addl Cleanup/Treatment info:
Address of Data Source:
Total ACRES Cleaned Up: .36
Number of Cleanup Jobs Leveraged:
EPA Cleanup Funding:
Leveraged Funding:
Cost Share Funding:
Total Funding:


Top of Page


Climate Adaption and Mitigation - Demolition or Cleanup

There is no data for Climate Adaption and Mitigation - Demolition or Cleanup.


Top of Page


Institutional and Engineering Controls

No
No
Yes
Other SSD system is in place
As part of the Due Care obligations regarding the known onsite contamination, completion of a Constructability Assessment to identify site specific building conditions which may require specific design approaches/components and an SSD Pilot Test was completed. The purpose of the system is to depressurize the atmosphere beneath the concrete slab of the subject building and maintain a greater pressure within the subject building that would prevent soil gas from entering the building and vent any soil gas beneath the concrete slab outside of the building. On October 20, 2020, PM completed a site inspection, and on January 12, 2021, PM conducted an SSD pilot test to determine the feasibility of an SSD system as a vapor mitigation remedy. Based on the SSD pilot test, the results, an SSD system is a technically feasible mitigation strategy to prevent vapor intrusion into the subject building and is recommended.
No


Top of Page


Redevelopment and Other Leveraged Accomplishments

There are no current redevelopment activities.


Number of Redevelopment Jobs Leveraged:
Actual Acreage of Greenspace Created:
Leveraged Funding:


Top of Page


Climate Adaption and Mitigation - Redevelopment

There is no data for Climate Adaption and Mitigation – Redevelopment


Top of Page


Additional Property Attributes

The vacant former gas station will be redeveloped into a new restaurant. Former Use: The subject property consists of four parcels totaling approximately .36 acres, and is located on the southwest corner of the intersection of South Washington Avenue and Elm Street in Lansing, Michigan. The subject property is occupied by a 1,813 square foot commercial building with associated paved parking and driveways and grass/vegetation covered areas. Standard and other historical sources were able to document a residential dwelling was present in the eastern portion in at least 1898. The former dwelling was demolished by 1925. The current building was constructed between 1921 and 1925 and operated as a gasoline service station from at last 1925 to the 1960s. Gasoline dispensing operations ceased in 1960 and the property operated as an automotive service business until 2000. Operations included automotive detailing from 2000 to 2004, personal storage from 2004 to 2014, and has been vacant or undergoing renovations with no business operations since 2014. Two former dwellings were constructed on the western portion between 1908 and 1913 and were demolished between 1975 and 1990. This portion of the property has been surface parking since that time.
Commercial (.21) Residential (.15)
Petroleum