Profile Information

Jacques Bldg, Lot 1 & B Twin Steeples Landing
Private
236650
2nd Ave NE DYERSVILLE, IA 52040
2.75
0731204001, 0731201007, 0731204014
42.4855148 / -91.1215615
2
Morris, Jennifer
Morris.Jennifer@epa.gov
913-551-7341


Top of Page


Property Location



Top of Page


Property Progress


Top of Page


CAs Associated with this Property

CA NameCA #StateTypeAnnouncement Year
East Central Intergovernmental AssociationBF97756401IAAssessment2016


Top of Page


Assessment Activities at this Property

ActivityEPA FundingStart DateCompletion DateCAAccomplishment Counted?Counted When?
Phase I Environmental Assessment$1,045.7502/26/201803/28/2018East Central Intergovernmental AssociationYFY20
Phase II Environmental Assessment$5,223.2506/26/201809/10/2018East Central Intergovernmental AssociationN
Supplemental Assessment04/25/201809/10/2018East Central Intergovernmental AssociationN
Supplemental Assessment$1,592.2007/25/201808/16/2018East Central Intergovernmental AssociationN


Is Cleanup Necessary? Yes
EPA Assessment Funding: $7,861.20
Leveraged Funding:
Total Funding: $7,861.20


Top of Page


Climate Adaption and Mitigation - Planning or Assessment

There is no data for Climate Adaption and Mitigation - Planning or Assessment.


Top of Page


Contaminants and Media


Asbestos
Cleaned Up
Building Materials
Cleaned Up

Cleanup Activities

Start DateEPA FundingCompletion DateCAAccomplishment Counted?Cleanup Documentation
10/03/201810/08/2018East Central Intergovernmental AssociationYes


Cleanup/Treatment Implemented: Y
Cleanup/Treatement Categories:
Addl Cleanup/Treatment info: EMS, Inc. abated and removed asbestos from the property
Address of Data Source:
Total ACRES Cleaned Up: 2.75
Number of Cleanup Jobs Leveraged: 0
EPA Cleanup Funding:
Leveraged Funding: $5,780.00
Cost Share Funding:
Total Funding: $5,780.00


Top of Page


Climate Adaption and Mitigation - Demolition or Cleanup

There is no data for Climate Adaption and Mitigation - Demolition or Cleanup.


Top of Page


Institutional and Engineering Controls

No
No
No


Top of Page


Redevelopment and Other Leveraged Accomplishments

Start DateLeveraged FundingCACompletion Date
11/20/2018$12,697,008.00East Central Intergovernmental Association04/28/2021
11/20/2018$786,000.00East Central Intergovernmental Association04/28/2021
11/20/2018$3,000,000.00East Central Intergovernmental Association04/28/2021
11/20/2018$689,677.79East Central Intergovernmental Association04/28/2021


Number of Redevelopment Jobs Leveraged:
Actual Acreage of Greenspace Created:
Leveraged Funding:


Top of Page


Climate Adaption and Mitigation - Redevelopment

There is no data for Climate Adaption and Mitigation – Redevelopment


Top of Page


Additional Property Attributes

Former Use: The property was previously privately owned commercial site consisting of an approximate 3,600 square foot, commercial building/warehouse situated on approximately 0.54 acres of land. The original structure located on the property was constructed circa 1900. An environmental site assessment revealed possible contaminants in the soil and asbestos in the building structure. However based on the proposed site reuse the detected contaminant levels were low and not deemed a concern. Dyersville Industries acquired the site, abated and demolished the building. The property was replatted and became part of the Twin Steeples Landing Plat. Site preparation for the area included bringing in 13,000 cu yards of fill to raise Twin Steeples Landing above flood level along North Fork Maquoketa River bank. Development of site began in 2019 and was completed in 2021. The original parcel was combined with portions of two other parcels and replatted into two new separate parcels: One parcel which is located along North Fork Maquoketa River includes a kayak launch area, riverwalk, retaining wall and greenspace. The second parcel was developed with a mixed-use multi-story building containing over 63,000 sf. First level underground offers over 35 parking spaces and main level is commercial use. The upper three floors contain 33 luxury apartment and condo units. Construction on building was completed in 2021.
Commercial (.54)
Petroleum
10/08/2018


Top of Page