Skip to Main Content
U.S. flag

An official website of the United States government


Profile Information

Sweet Peaks
Private
256821
343 Main Street KALISPELL, MT 59901
.17
48.194984369071 / -114.312140948284
1
Rothenmeyer, William
Rothenmeyer.William@epa.gov
303-312-6045


Top of Page


Property Location



Top of Page


Property Progress


Top of Page


CAs Associated with this Property

CA NameCA #StateTypeAnnouncement Year
MT Department of Environmental Quality4B95815270MTAssessment2022
Montana West Economic Development FoundationBF00I15100MTAssessment2023
R8 TBA - Montana (STAG Funded)n/aMTTBA2004


Top of Page


Assessment Activities at this Property

ActivityEPA FundingStart DateCompletion DateCAAccomplishment Counted?Counted When?
Cleanup Planning$11,250.0006/20/202409/09/2024Montana West Economic Development Foundation
Phase I Environmental Assessment$5,000.0006/20/202408/01/2024Montana West Economic Development Foundation
Phase I Environmental Assessment$4,582.7606/07/202311/02/2023MT Department of Environmental Quality
Phase II Environmental Assessment$213,700.0011/20/202007/24/2023R8 TBA - Montana (STAG Funded)YFY24


Is Cleanup Necessary? Yes
EPA Assessment Funding: $234,532.76
Leveraged Funding:
Total Funding: $234,532.76


Top of Page


Climate Adaption and Mitigation - Planning or Assessment

Selected Strategy(ies)Explanatory Text
N/AThis property does not incorporate planning or assessment activities to address impacts from extreme weather events and natural disasters. If no activities were incorporated, select this option.


Top of Page


Contaminants and Media


Petroleum Products
PAHS
Petroleum Products
SVOCs
VOCs
NOT Cleaned up
NOT Cleaned up
NOT Cleaned up
NOT Cleaned up
NOT Cleaned up
Petroleum Products
Ground Water
Soil
NOT Cleaned up
NOT Cleaned up

Cleanup Activities

There are no current cleanup activities.


Cleanup/Treatment Implemented:
Cleanup/Treatement Categories:
Addl Cleanup/Treatment info:
Address of Data Source:
Total ACRES Cleaned Up: .17
Number of Cleanup Jobs Leveraged:
EPA Cleanup Funding:
Leveraged Funding:
Cost Share Funding:
Total Funding:


Top of Page


Climate Adaption and Mitigation - Demolition or Cleanup

Selected Strategy(ies)Explanatory Text
N/AThis property does not incorporate demolition or cleanup activities to address impacts from extreme weather events and natural disasters. If no activities were incorporated, select this option.


Top of Page


Institutional and Engineering Controls

No
No


Top of Page


Redevelopment and Other Leveraged Accomplishments

There are no current redevelopment activities.


Number of Redevelopment Jobs Leveraged:
Actual Acreage of Greenspace Created:
Leveraged Funding:


Top of Page


Climate Adaption and Mitigation - Redevelopment

Selected Strategy(ies)Explanatory Text
N/AThis property does not incorporate redevelopment activities to address impacts from extreme weather events and natural disasters. If no activities were incorporated, select this option.


Top of Page


Additional Property Attributes

Phase II included tank removal, and contaminated soil removal in coordination with Montana DEQ and Petroboard. All accessible contaminated soils removed. Soils left in place could not be removed without compromising stability of surrounding structures and infrastructure. Groundwater impacts from release caused sump to be installed in adjacent building. Soil and groundwater concentrations at this site exceed DEQ levels and therefore an NFA letter is not going to be issued at this time. A prospective new owner will purchase the property on September 16, 2024. Phase I ESA and cleanup planning completed for prospective owner.
Commercial (.17)


Top of Page