60141
30 Washington Street Becket, MA 01223
.26
39 0
42.2964905 / -73.1558267
1
Warren, Joellyn
jwarren@berkshireplanning.org
4134421521


Top of Page


Property Location



Top of Page


Property Progress


Top of Page


CAs Associated with this Property

CA NameCA #StateTypeAnnouncement Year
Berkshire Regional Planning Commission2B96110001MAAssessment2009
Berkshire Regional Planning CommissionBF97119601MAAssessment2004
Berkshire Regional Planning CommissionBF96177301MAAssessment2013
Berkshire Regional Planning CommissionBF97180301MAAssessment2007


Top of Page


Assessment Activities at this Property

ActivityEPA FundingStart DateCompletion DateCAAccomplishment Counted?Counted When?
Phase I Environmental Assessment$2,500.0006/22/200609/14/2006Berkshire Regional Planning CommissionYFY06
Phase II Environmental Assessment$95,500.0001/01/2008Berkshire Regional Planning CommissionN
Supplemental Assessment$91,421.0008/26/200906/15/2012Berkshire Regional Planning CommissionN
Supplemental Assessment$14,000.0005/07/2015Berkshire Regional Planning CommissionN


Is Cleanup Necessary? No
EPA Assessment Funding: $203,421.00
Leveraged Funding:
Total Funding: $203,421.00


Top of Page


Climate Adaption and Mitigation - Planning or Assessment

There is no data for Climate Adaption and Mitigation - Planning or Assessment.


Top of Page


Contaminants and Media


Petroleum Products
NOT Cleaned up
Ground Water
Soil
NOT Cleaned up
NOT Cleaned up

Cleanup Activities

There are no current cleanup activities.


Cleanup/Treatment Implemented:
Cleanup/Treatement Categories:
Addl Cleanup/Treatment info:
Address of Data Source:
Total ACRES Cleaned Up: .26
Number of Cleanup Jobs Leveraged:
EPA Cleanup Funding:
Leveraged Funding:
Cost Share Funding:
Total Funding:


Top of Page


Climate Adaption and Mitigation - Demolition or Cleanup

There is no data for Climate Adaption and Mitigation - Demolition or Cleanup.


Top of Page


Institutional and Engineering Controls

No
No
No
No


Top of Page


Redevelopment and Other Leveraged Accomplishments

There are no current redevelopment activities.


Number of Redevelopment Jobs Leveraged:
Actual Acreage of Greenspace Created:
Leveraged Funding:


Top of Page


Climate Adaption and Mitigation - Redevelopment

There is no data for Climate Adaption and Mitigation – Redevelopment


Top of Page


Additional Property Attributes

A Phase I was conducted under BF971196010. A Phase II was initiated under BF-97180301-0. A Supplemental Phase II and Class C Response Action Outcome report was completed under 2B-9611001-1.

Former Use: The site is an approximate 0.26-acre, teardrop-shaped parcel of land located in a predominately rural/residential area. The site was developed in the early 1900s and has been used as a variety store and a retail gasoline station since. An automobile service garage was also present at the site approximately 60 years ago. The site is occupied by a two-story wooden structure, featuring a small utility basement and crawl space. A small, one-story addition, with a slab-on-grade construction, is located adjacent to the northwest of the main structure. In July 2003 the store closed due to the owner's inability to operate the store. The convenience store re-opened in July 2010 by a lessee followed by the removal of two 2,000-gallon gasoline USTs in October 2010. The Site reached Permanent Closure through MNA in October 2015.
Commercial (.26)
Petroleum
10/21/2015


Top of Page