Avondale Right-of-Way | $0.00 | 10/02/2007 | Phase I Environmental Assessment | $5,231.25 |
Avondale Right-of-Way | $0.00 | 11/30/2008 | Phase II Environmental Assessment | $63,424.60 |
City of Apache Junction Business Park | $7,500.00 | | Phase I Environmental Assessment | $0.00 |
City of Winslow- Clear Creek Pump Station Property | $7,500.00 | | Phase I Environmental Assessment | $0.00 |
City of Winslow- Former Wood Treatment Facility | $7,500.00 | | Phase I Environmental Assessment | $0.00 |
Cochise County Airport | $4,950.00 | 07/08/2008 | Phase I Environmental Assessment | $0.00 |
Cochise County Airport | $43,824.14 | 06/18/2009 | Phase II Environmental Assessment | $0.00 |
Downtown Connection Center (Tax Lot 100-43-003B) | $0.00 | 01/03/2007 | Phase I Environmental Assessment | $2,954.00 |
Downtown Connection Center (Tax Lot 100-43-003B) | $0.00 | 06/30/2008 | Phase II Environmental Assessment | $88,766.04 |
Former Wickenburg Landfill | $0.00 | 02/29/2008 | Phase II Environmental Assessment | $72,515.62 |
Gorman Avenue Cemetery Expansion | $0.00 | 11/29/2007 | Phase II Environmental Assessment | $51,834.03 |
Greenlee County Airport | $7,500.00 | | Phase I Environmental Assessment | $0.00 |
Show Low Library Site | $0.00 | 12/12/2008 | Phase I Environmental Assessment | $4,950.00 |
Show Low Library Site | $0.00 | 06/25/2009 | Phase II Environmental Assessment | $61,400.00 |
Special Planning Area 1 Water Reclamation Facility | $0.00 | 06/11/2009 | Phase II Environmental Assessment | $63,931.01 |
St. Johns Cemetery Expansion | $0.00 | 06/24/2008 | Phase II Environmental Assessment | $37,811.00 |
St. Johns City Hall | $0.00 | 12/26/2008 | Phase I Environmental Assessment | $4,950.00 |
St. Johns City Hall | $0.00 | 06/25/2009 | Phase II Environmental Assessment | $66,750.00 |
Standin' on the Corner Park | $0.00 | 01/13/2006 | Phase I Environmental Assessment | $2,395.00 |
Standin' on the Corner Park | $0.00 | 06/13/2006 | Phase II Environmental Assessment | $17,303.00 |
Standin' on the Corner Park | $0.00 | 07/06/2007 | Supplemental Assessment | $315,000.00 |
Town of Youngtown- former Public Works Yard | $7,000.00 | | Phase I Environmental Assessment | $0.00 |
Town of Youngtown- former RV repair site | $7,000.00 | | Phase I Environmental Assessment | $0.00 |