Cleanup Activities
Start Date | EPA Funding | Completion Date | CA | Accomplishment Counted? | Cleanup Documentation |
05/26/2020 | $123,000.00 | 12/22/2020 | Kennebec Valley Council of Governments | No | |
Cleanup/Treatment Implemented:
Y
Cleanup/Treatement Categories:
Addl Cleanup/Treatment info:
Remedial actions removed asbestos-containing materials from the building and a 12-inch layer of lead-contaminated soil in building footprint. Lead contamination remains below the 12-inch layer and is subject to a ME DEP-approved cover system, which has been installed. A maintenance plan for the cover system, as well as an Environmental Media Management Plan were submitted through ME DEP VRAP and approved by ME DEP.
Address of Data Source:
Total ACRES Cleaned Up: .25
Number of Cleanup Jobs Leveraged: 0
EPA Cleanup Funding: $123,000.00
Leveraged Funding:
Cost Share Funding:
Total Funding: $123,000.00